In today’s world all the power
utilities are unbundled and de-regulated to a certain extent. The price of
electricity is the most important factor to nearly all the market participants.
The most basic electricity pricing mechanism is the Market Clearing Price
(MCP).
In a power market, after
receiving the bids, the System Operator (SO) aggregates the supply bids into a
supply curve ‘S’ and aggregates the demand
bids into a demand curve ‘D’. The
intersection of S and D is the Market
Clearing Price (MCP)
Generally when there is no transmission congestion, MCP is the same for the entire power system, but when there is congestion, the concept of Zonal Market Clearing Price (ZMCP) or Locational Marginal Price (LMP) is used. In other words when there is no congestion, the LMP is the same as the MCP but in the congested state, the marginal cost of each bus is the LMP.
Generally when there is no transmission congestion, MCP is the same for the entire power system, but when there is congestion, the concept of Zonal Market Clearing Price (ZMCP) or Locational Marginal Price (LMP) is used. In other words when there is no congestion, the LMP is the same as the MCP but in the congested state, the marginal cost of each bus is the LMP.
Let’s have a look into the LMP concept using a small example. A small 4 bus system is shown in the figure below.
Fig. A four bus system.
The system has 4 buses with 2
generators each of capacity 125 MW at bus 1 and 3. A load of 100 MW is
connected at bus 4. Suppose that there is no congestion and no losses, then for
supplying 100 MW of load at bus 4, the power flows in line –
1-2 is 25 MW,
2-3 is 25 MW,
3-4 is 25 MW, and
1-4 is 75 MW if the lines are
identical.
As per the definition, LMP at any node or bus
is the cost of supplying add 1 MW at that node. Suppose we have to calculate
the LMP at node 4. When there is no congestion and no losses, the power flow in
the lines are –
25.25 MW at line 1-2,
25.25 MW at line 2-3,
25.25 MW at line 3-4, and
75.75 MW at line 1-4.
Thus, the additional load of 1 MW
at node 4 is supplied by generator 1 at it’s offer price of 300 INR. This generator
is the marginal generator and the LMP at node 4 is 300 INR.
LMP when there is Congestion in
Lines:
Now suppose that the maximum flow
through line 1-4 is limited to 75.2 MW. In this case, to meet the additional 1
MW load at node 4, the generators have to re-scheduled as the old scheduling
will overload line 1-4. As per the new scheduling, which can be obtained by
running Optimum Power Flow (OPF), the output of generator 1 is to be reduced by
0.1 MW and generator 3 has to supply 1.1 MW. The new line flows are-
24.7 MW in line 1-2,
24.7 MW in line 2-3,
25.8 MW in line 3-4, and
75.2 MW in line 1-4.
Thus, the LMP at node 4 can be
calculated as
(1.1 x 350) – (0.1 x 300) = 355
INR
Similarly, the LMP at other buses can be calculated. Now I think that the calculation
of LMP is clear to you.
No comments:
Post a Comment