An electrical substation:
An electrical substation is a combination of a number of major electrical equipments like power transformers, circuit breakers, instruments transformers, bus bars, lightning arresters, control panels, interconnecting cables, capacitor banks, battery set, and other related equipments designed as per the requirements, size, capacity and class of the substation.
Control room is provided to house the various control panels and battery backup and to station the employ/operator.
Power transmission and distribution in densely populated urban areas is a great challenge because of land availability and low noise and electromagnetic limitations. With the development in technology and enough improvement in substation design, Gas Insulated Substations are finding increasing use because of their safety, reliability, less space requirement and enhanced life.
Factors affecting the Layout and Design of a substation:
An electrical substation is a combination of a number of major electrical equipments like power transformers, circuit breakers, instruments transformers, bus bars, lightning arresters, control panels, interconnecting cables, capacitor banks, battery set, and other related equipments designed as per the requirements, size, capacity and class of the substation.
Control room is provided to house the various control panels and battery backup and to station the employ/operator.
Power transmission and distribution in densely populated urban areas is a great challenge because of land availability and low noise and electromagnetic limitations. With the development in technology and enough improvement in substation design, Gas Insulated Substations are finding increasing use because of their safety, reliability, less space requirement and enhanced life.
Factors affecting the Layout and Design of a substation:
The
physical layout and the design of the substation are governed by:
1. The number of incoming and
outgoing feeders (existing and proposed)
2. Existing and expected load demand
on the substation,
3. Soil resistivity,
4. Expected fault levels at 33 kV
and 11 kV level ,
5. Climatic conditions, such as
temperature, altitude, rainfall etc.
Governing Rules & Regulations:
All electrical and civil works related to the installation and commissioning of an electric substation shall be carried out in accordance to the provisions given in Indian Electricity Act 2003 and the Indian Electricity Rule 1956 amended upto date.
The standard instruction for construction of 33/11 kV substation is given in REC standards which specifies the layout along with the switchgear. The standard layout guides for the general arrangement of the equipments, structures, bus-bars etc. of outdoor substations. The general specifications of a substation cover the details of the major equipments and other items to be supplied.
All electrical and civil works related to the installation and commissioning of an electric substation shall be carried out in accordance to the provisions given in Indian Electricity Act 2003 and the Indian Electricity Rule 1956 amended upto date.
The standard instruction for construction of 33/11 kV substation is given in REC standards which specifies the layout along with the switchgear. The standard layout guides for the general arrangement of the equipments, structures, bus-bars etc. of outdoor substations. The general specifications of a substation cover the details of the major equipments and other items to be supplied.
The tender for a
particular substation clearly indicate these specifications. The tender
specification also has the reference drawings, which indicate the schematic of
major connections and form the part of the specification. Suitable provisions
can be made in the switchyard depending upon the local condition and locations
so as to facilitate transportation of heavy equipments, especially power
transformers. While carrying out the substation construction all the labour
regulations, safety codes and measures must be followed.
Number of Transformers and Feeders in a substation:
Number of Transformers and Feeders in a substation:
The
REC standard mentions that an outdoor type 33/11 kV substation should have 2
power transformers and 3 outgoing feeders. There must be provision for 2
additional 11 kV outgoing feeder for load enhancements in future. The number of
33 kV incoming feeder may be one or two depending upon the requirement. The
various arrangements for the 33 kV incoming and outgoing lines may be according
to the standard practice adopted by the electricity board.
Fig.1: The power transformer, circuit breakers, gantry of an under construction 33/11 kV substation in rural area.
Control Panels:
All
the control and equipments needed to monitor and remote control the vital
equipments such as transformers, circuit breakers, feeders etc. are housed in
control panels. In these control panels, relays, meters, and
instruments are mounted as per the drawing arrangements. Separately earthed and
effectively segregated compartments/ panels (earthed panels) should be provided
for circuit breaker, bus-bars, relays, CTs ,PTs etc so that faults in any one
panel do not cause damage to other equipments or panels.
Relays:
Relays:
Relays are the sensing device which sense the abnormal condition in any power system and accordingly give alarm and trip signal to circuit breaker. The different relays used normally in a 33/11 kV sub-station are earth fault relay, and over-current relay. Earlier electro-mechanical relays were used which are now being replaced.
The
relays used in modern substation are of microprocessor based numerical relays
with overload, earth fault and short circuit protection. 24/30 V DC supply
with battery pack and battery charger is used for the protection as well as
indication circuits.
Current Transformers (CTs) and Potential Transformers (PTs):
Current Transformers (CTs) and Potential Transformers (PTs) used for metering and protection purpose. They should be of the burden more than the minimum burden mentioned and of accuracy class 0.5.
Earthing of a Sub-station:
Fig.2: Control Panel with old Electro-mechanical relays.
Current Transformers (CTs) and Potential Transformers (PTs):
Current Transformers (CTs) and Potential Transformers (PTs) used for metering and protection purpose. They should be of the burden more than the minimum burden mentioned and of accuracy class 0.5.
Earthing of a Sub-station:
The
earthing of a substation is of prime importance for the satisfactory operation
of protective devices and for the safety of equipments and personnel. All equipments
must have separate earthing and in the numbers given in the manual. These earths
should be well connected to each other and should form a grid. The resistance
of the earthing should be maintained at the required minimum value.
There
should be satisfactory drainage facility in the yard so that accumulation of
rain water should not take place. Yard should be covered with granite metal to
prevent the growth of grass and weeds, formation of mud etc. the substation may
also have capacitor banks of appropriate capacity to improve the power factor
and to control the harmonics.
Inspection
is necessary before dispatch, delivery at site, installation, commissioning,
putting into operation and handing over the equipments.
Halo,I'm Helena Julio from Ecuador,I want to talk good about Le_Meridian Funding Service on this topic.Le_Meridian Funding Service gives me financial support when all bank in my city turned down my request to grant me a loan of 500,000.00 USD, I tried all i could to get a loan from my banks here in Ecuador but they all turned me down because my credit was low but with god grace I came to know about Le_Meridian so I decided to give a try to apply for the loan. with God willing they grant me loan of 500,000.00 USD the loan request that my banks here in Ecuador has turned me down for, it was really awesome doing business with them and my business is going well now. Here is Le_Meridian Funding Investment Email/WhatsApp Contact if you wish to apply loan from them.Email:lfdsloans@lemeridianfds.com / lfdsloans@outlook.comWhatsApp Contact:+1-989-394-3740.
ReplyDeleteIt sounds really good. Thanks for the great information. I have read many blogs but this blog is really informative. I got a lot of knowledge from this.Best Quality Distribution Transformer Manufacturers
ReplyDelete"Fantastic post! The details on electrical substations and electrician services are very well explained. Really appreciate the thoroughness." Contact with Family First Electrical's Electrician in Lilyfield for professional advice on any electrical concern.
ReplyDelete