"Protective equipments including relays are in-operative most of their useful life."
They operate only under fault conditions. Testing of protective gears thus pose a problem. Testing of protective relays under normal operating condition normally does not give realistic results. Hence defects may easily pass undetected until revealed by incorrect operation or no operation on occurrence of actual fault.
Question arises why the relays or
any other protective devices or gears are tested?
Testing of relays is usually done to ensure that:
Testing of relays is usually done to ensure that:
1)
The relay will operate correctly so as to clear
a fault, and
2) The relay will remain in-operative on faults
outside its specified zone.
Now let’s talk about the various
tests that are necessary for a protective gear and relay. Broadly the tests that are conducted on a relay are:
1) Factory Test: For testing of a relay, the
operational condition of the system during faults must be closely reproduced. The
plant supplying the current for these tests particularly for high speed
protection must be of sufficient capacity and design. Relay test benches are
used for light current tests, and heavy current tests are carried out with the
relays and CTs connected operationally.
Factory test
also include many other tests such as material investigation, effects of
impacts and vibration, resistance to atmospheric corrosion, effects of temperature
and dust, tightness of relay case etc.
2) Installation or Commissioning Test: The
main purpose of commissioning tests is to prove that the relay has been
properly installed and connected and it functions correctly and is ready for
service. Comprehensive tests at sites of many other elements associated with
the protective relays and which may have been supplied by different suppliers,
are of great importance (Eg. Ratio and polarity test of CTs and PTs).
These tests
include the general inspection of the equipment, checking of all connections
etc. Insulation resistance of all the circuits is measured and the relay is
tested by secondary injection. Further these tests at the site provide a check
over the components which have passed factory tests and have been transported
safely.
3) Periodic Maintenance Test: Moisture and
dust tend to produce deterioration of insulation, increase resistance of
contacts, stickiness of relay bearings and pivots. A general inspection of the
physical condition of all equipments, a check of accessible connections
including fuses and links, secondary injection tests of relays, functioning
test of logic and trip circuits are included in this test. The operation of
indicating and alarm circuits should also be checked during this test.
No comments:
Post a Comment